How long does it take to build an ADU in the Bay Area

Argi Avetisyan
Argi Avetisyan
Gather ADU expert
How long does it take to build an ADU in the Bay Area
Not sure where to start with your ADU project?

Schedule a free appointment with one of our ADU experts.

Book a call

Accessory Dwelling Units (ADUs) are becoming increasingly popular among Bay Area homeowners. With skyrocketing property prices and a pressing need for affordable housing, ADUs offer a practical solution. But how long does it actually take to build one? This blog will walk you through the entire process and what you can expect at each stage.

The Rise of ADUs in the Bay Area

ADUs, also known as granny flats or in-law units, have seen a significant rise in popularity. These small, self-contained homes are built on the same lot as an existing property. They can serve multiple purposes—from housing extended family to generating rental income or even serving as a home office.

Addressing Housing Shortages and Affordability

The Bay Area is infamous for its housing crisis. ADUs provide a viable solution by increasing the housing supply without the need for large-scale developments. They offer a more affordable alternative for tenants and add value to the homeowner's property.

The Construction Process of an ADU

Building an ADU involves several steps, each crucial to the project's success. From planning to final inspection, each stage has its own set of requirements and timelines.

Planning and Permits

One of the first steps in building an ADU is planning. This involves understanding local zoning laws and securing the necessary permits. The planning stage can take anywhere from 2 to 4 months, depending on the complexity and scope of the project.

Design and Customization

Once permits are in place, the next step is designing your ADU. Many homeowners opt for customized designs to meet their specific needs. This stage can add another 1 to 2 months to the timeline.

Construction Begins

With the design finalized and permits secured, construction can begin. The time required for this stage varies greatly, depending on whether you're opting for a prefab unit or a stick-built one.

Inspections and Final Approvals

After construction, the ADU must pass multiple inspections to ensure it meets all building codes and regulations. This step can take an additional 1 to 2 months.

Factors Affecting ADU Construction Timeline

Several factors can influence how long it takes to build an ADU. These include the size and design of the unit, local regulations, and whether the unit is prefab or stick-built.

Size and Design Choices

Larger, more complex ADUs naturally take longer to build. Custom designs also add to the timeline compared to standardized models.

Local Regulations and Permitting

Navigating local regulations and obtaining permits can be time-consuming. Each municipality has its own set of rules, which can either expedite or delay the process.

Prefab vs Stick-Built

Prefab units are typically quicker to complete because they are manufactured offsite. Stick-built units, constructed entirely onsite, are subject to weather delays and other unforeseen issues.

Typical Timeframe for Building an ADU

On average, constructing an ADU in the Bay Area takes about seven to twelve months. This includes everything from initial planning to final inspection. Prefab models tend to be on the shorter end of this range, while custom, stick-built units can extend towards the longer end.

Real-Life Examples of ADU Construction Timelines

ADU in Bay Area

Let's look at some real-life examples to give you a better idea of what to expect.

Case Study 1

Project Overview: A 500 sqft prefab ADU with a simple design.

Timeline: 8 months from start to finish.

Challenges: Minimal delays due to streamlined prefab construction.

Case Study 2

Project Overview: A 750 sqft custom ADU with unique architectural features.

Timeline: 12 months from start to finish.

Challenges: Multiple design revisions and weather-related delays.

Case Study 3

Project Overview: A 600 sqft stick-built ADU with standard amenities.

Timeline: 10 months from start to finish.

Challenges: Navigating local permitting processes added time.

Tips for Streamlining the ADU Building Process

Building an ADU doesn't have to be a lengthy ordeal. Here are some tips to help you streamline the process.

Plan Ahead

Start planning as early as possible. Understand the local regulations and zoning laws to avoid unexpected delays.

Choose a Reliable Contractor

Hiring a reputable contractor who specializes in ADUs can make a big difference. They will have experience navigating local regulations and can help expedite the process.

Opt for Prefab Models

If time is a critical factor, consider opting for a prefab ADU. These units are constructed offsite, minimizing on-site delays.

The Future of ADUs in the Bay Area

The demand for ADUs in the Bay Area is expected to grow as more homeowners recognize their benefits. From addressing housing shortages to providing affordable living options, ADUs are a crucial part of the solution.

Building an ADU is a significant investment of time and resources, but with careful planning and the right team, it can be a rewarding experience.

Ready to get started on your ADU project? Get a quote for your ADU project!

Popular ADU Floorplans

Malibu
Malibu
1,000 SQFT
3 Bed / 2 Bath
Monterey
Monterey
750 SQFT
2 Bed / 1 Bath
Topanga
Topanga
600 SQFT
1 Bed / 1 Bath
Carmel
Carmel
500 SQFT
1 Bed / 1 Bath
Sonoma
Sonoma
400 SQFT
1 Bed / 1 Bath
Marina
Marina
300 SQFT
Studio / 1 bath
gather adu team